Reconstruction of „B15“ in the area of Essenbach/Germany by MAX STREICHER GmbH & Co. KG aA/branch Landshut

Within a consortium the branch Landshut of MAX STREICHER GmbH & Co. KG aA has restructured a 9.5 km section of the main road „B15“ between Ergoldsbach and Essenbach.

About 15,000 vehicles pass this section of the „B15“ daily, which connects the city Landshut with the junction of the „B15neu“ in Ergoldsbach. During the reconstruction works it wasn’t permitted to interrupt the traffic flow, with the exception of a complete closure during the last two weeks of the summer holidays.

As part of the reconstruction of the whole crossing of Essenbach with a length of 1.2 km, a cycle path and parking area were installed, the sidewalk was restructured and two junctions including traffic lights were rebuilt. The contract also included the reconstruction of a 500 m section of the road „St2141“. The asphalt mixtures for all construction activities of STREICHER were delivered by the company’s own asphalt mixing plant nearby Unterwattenbach.

Considering the detailed civil works and several modifications of the offered services the construction time of five months was very short. So some construction phases had to be carried out simultanously. In the beginning of October the project was scheduled on time to the client Staatliches Bauamt Landshut.

Reconstruction "B15"