Execution of the pipeline WAL as connection to the first LNG terminal of Germany (high speed project)
by MAX STREICHER GmbH & Co. KG aA
Length: 12.3 km, DN 1000
Scope of work: pipeline construction, civil engineering, extensive dewatering, 12 trenchless crossings using different methods (thrustboring and direct pipe method)
Specific features:
Very short execution period till mechanical completion (five months), therefore six-day working week necessary; extremely hydrated soils (construction roads with large distance to pipe trench, elaborate dewatering and sheet pile works)
Execution of an onshore natural gas pipeline in Jutland, Denmark
by MAX STREICHER GmbH & Co. KG aA in a joint venture
Length: 60 km; DN 800, DN 900, DN 1000
Wall thickness: 12.0 - 40.0 mm
Scope of work: valve and pig stations, crossings using the micro-tunneling, (CFA) continuous flight auger drilling and pipe jacking method, pipe and civil engineering work and comprehensive dewatering
Construction of gas pipeline ZEELINK between Aachen and Mönchengladbach
(infrastructure project within the change of L to H gas)
Length: 216 km in total; approx. 61 km, DN 1000 executed by
MAX STREICHER GmbH & Co. KG aA within a joint venture
Scope of service: civil engineering, pipe works as well as seven extensions, construction of a gas pressure regulating station, crossings in different methods (micortunneling, direct pipe, thrust boring etc. )
Construction of a gas pipeline between Pleyben and Priziac
Length: approx. 56 km, DN 400
Scope of work: civil engineering, pipe works, crossings (different methods), transmission station
Within a joint venture
Construction of gas pipeline EUGAL between Lubmin on the Baltic Sea and Deutschneudorf on the Saxon-Czech border
Length: 480 km in total; 291 km, DN 1400 executed by MAX STREICHER GmbH & Co. KG aA within a joint venture
Scope of service: civil engineering, drillings, crossings, valve, pig, pump stations
Construction of EUSAL pipeline between Erftstadt and Euskirchen
(infrastructure project within change of L- to H-gas)
Length: 18.5 km, DN 400
Scope of work: civil engineering, pipe works, gas pressure and regulating stations Kuchenheim and Lechenich, crossings using different methods (microtunneling, thrust boring etc.)
Construction of a pipeline from Cervignano to Mortara - Lots 1 and 2
Length about 62 km, DN 1400
Scope of work: civil engineering and pipeline construction, including valve and pig stations
Crossings were built using different methods (microtunneling, direct pipe, open trench)
Construction of a natural gas pipeline (section 3)
Scope of service: All pipeline works (lining, bending, pipe delivery, nondestructive testing, isolation, lowering, connecting, pressure testing, assembly of valve stations) and many other services
Length: 46 km; DN 1200; DP 100; wall thickness: 22.2 mm
Additional services: Pulling in a pipe string to create the culvert for the Inn and Innwerkkanal underpass as a subcontractor (section 2)